http://www.crainsdetroit.com/article...rning-20171109
(Judge) Ludington last week said the township's interpretation of noise standards was reasonable, even if others might have a different opinion.
Tuscola Wind III is controlled by wind giant NextEra Energy Resources. After new trustees were elected in 2016, Almer Township rejected a permit that would have cleared the way for 19 turbines. It's part of a larger wind project with 55 turbines in three townships.
The residents of that area pushed back hard against a planned wind turbine farm in their community. Hard to blame them. The damn things are an eyesore, not to mention loud.